Wind Energy Project

2 Documents in Project

Summary

SCH Number
2007122061
Lead Agency
Fairfield Suisun Sewer District
Document Title
Wind Energy Project
Document Type
NOD - Notice of Determination
Received
Posted
3/3/2008
Present Land Use
Utility
Document Description
The District is proposing to implement a wind energy project that would provide up to 113,000 kilowatt-hours of wind energy power annually to offset some of the electrical demands of the District's wastewater treatment plant operations; thereby decreasing its carbon footprint for energy use consumption. Specifically, The District is proposing to install and operate four (4) 50-kW turbines that would harness renewable wind energy resources and provide total generation capacity of up to approximately 200-kW of renewable electricity. Each of the four turbines would be approximately 100-feet tall and would have a three blade rotor with a diameter of 50 feet. The power generated by the proposed project would be collected and conveyed to a power substations through wires in underground conduits that would be installed as part of the proposed project. The proposed project would be located entirely on the District's wastewater treatment plant property which is within the City of Fairfield.

Contact Information

Name
Greg Baatrup
Agency Name
Fairfield Suisun Sewer District
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
Chadbourne Road and Cordelia Road
Zip
94534-9700
State Highways
Highway 12 and I-80

Notice of Determination

Approving Agency
Fairfield-Suisun Sewer District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.