Diamond Springs Parkway Phase 1B - Geotechnical Investigation (Lake or Streambed Alteration Agreement No. 1600-2016-0226-R2)

9 Documents in Project

Summary

SCH Number
2007122033
Lead Agency
El Dorado County
Document Title
Diamond Springs Parkway Phase 1B - Geotechnical Investigation (Lake or Streambed Alteration Agreement No. 1600-2016-0226-R2)
Document Type
NOD - Notice of Determination
Received
Posted
12/5/2016
Present Land Use
Industrial

Document Description
CDFW has executed Lake and Streambed Alteration Agreement No. 1600-2016-0226-R2, pursuant to section 1602 of the Fish and Game Code to the project Applicant, the El Dorado County Community Development Agency, as represented by Mr. Dustin Harrington. The project proposes to excavate up to 3 test pits to be used for a geotechnical investigation in preparation for the future installation of a culvert crossing associated with the Diamond Springs Parkway project. Each test pit will measure approx. 5 feet wide, ten feet long, and 12 feet deep. Subsurface material will be observed, and small samples will be collected for lab analysis. Following excavation, observation, and sampling, the excavated material will be replaced, and the test pit location restored to its original condition. The test pits will be situated in such a way that woody vegetation will not be removed, and excavated when no water is present within the stream.

Contact Information
Gabriele Quillman
CDFW
1701 Nimbus Road, Suite A
Rancho Cordova, CA 95670

Phone : (916) 358-2955

Location

Cities
Diamond Springs
Counties
El Dorado
Cross Streets
SR 49 (Diamond Road) and Pleasant Valley Road
Zip
95667
Parcel #
several
State Highways
Hwy 49, 50
Railways
Sacramento-Placerville
Schools
Herbert Green Middle
Other Information
Sections Continued: 30,19

Notice of Determination

Approving Agency
CDFW
Approving Agency Role
Responsible Agency
Approved On
Final Environmental Document Available at
1701 NImbus Road, Suite A, Rancho Cordova, CA 95670

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Download CSV New Search