Agreement Among the DWR, County of Kings and Kettleman City Community Services District for Construction, Operation and Maintenance of the Kettleman City Turnou
7 Documents in Project
Summary
SCH Number
2007121098
Lead Agency
Kettleman, City of
Document Title
Agreement Among the DWR, County of Kings and Kettleman City Community Services District for Construction, Operation and Maintenance of the Kettleman City Turnou
Document Type
NOD - Notice of Determination
Received
Posted
11/20/2015
Present Land Use
Vacant and highly disturbed land with existing dirt roadways transecting the project sites/Phase 1 zoning- Limited Agriculture Phase zoning- Highway Commercial
Document Description
For the overall project, KCCSD proposes to construct a Surface Water Treatment Plant and a Commercial Water Tank Facility. The proposed project will be constructed in two phases and will be connected via pipeline to the existing KCCSD water lines. A portion of the project requires a turnout on Reach 8D of the California Aqueduct. The siphon turnout will take water from the California Aqueduct to a planned surface water treatment plant located nearby. The proposed turnout requires a construction, operation and maintenance agreement with DWR.
Contact Information
Name
Craig Trombly
Agency Name
DWR
Contact Types
Lead/Public Agency
Phone
Location
Coordinates
Cities
Kettleman
Counties
Kings
Cross Streets
Phase 1-Fourth Street & General Petroleum Avenue Phase 2-Cyril Place & Hubert Way
Zip
93239
Total Acres
ph1- 5; ph2- 2
Parcel #
Ph. 1-042100103; Ph. 2-042150072
State Highways
Hwy 41 and I-5
Schools
Kettleman City ES
Waterways
California Aqueduct
Township
22
Range
19
Base
MDB&M
Other Information
Section Cont'd: 19, Ph: 2-30
Notice of Determination
Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes