PacifiCorp's Morrison Creek Substation Project

3 Documents in Project

Summary

SCH Number
2007112094
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
PacifiCorp's Morrison Creek Substation Project
Document Type
NOD - Notice of Determination
Received
Posted
3/14/2008
Present Land Use
The Proposed Project is located entirely within the jurisdiction of Del Norte County. The existing Simonson Substation and the proposed Morrison Creek Substation site is zoned Manufactoring and Industrial (M), with the County land use designation of General Information (GI). The proposed Morrison Creek Substation site is currently vacant and was previously used by a lumber mill operation.
Document Description
Through its CPUC application (A.07-07-018) filed on July 20, 2007, PacifiCorp seeks a Permit to Construct (PTC) the proposed Morrison Creek Substation and remove the existing Simonson Substation. The existing Simonson Substation, which currently steps power down from 69 kilovolt (kV) to 12.5 kV, would be replaced with the proposed Morrison Creek Substation which would have the same distribution capabilities. The objective of the Proposed Project is to increase system reliability for area customers.

Contact Information

Name
Michael Rosauer
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Counties
Del Norte
Cross Streets
US Highway 101 and Rowdy Creek Road
Zip
95567
Total Acres
~2
Parcel #
Multiple
State Highways
US Highway 101
Waterways
Rowdy Creek
Other Location Info
City/Nearest Community: Smith River

Notice of Determination

Approving Agency
California Public Utilities Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print