Folsom Boulevard Specific Plan

2 Documents in Project

Summary

SCH Number
2007112018
Lead Agency
City of Rancho Cordova
Document Title
Folsom Boulevard Specific Plan
Document Type
NOD - Notice of Determination
Received
Posted
6/19/2008
Present Land Use
Residential, Commercial, Office, Mixed Use
Document Description
Adoption of the Folsom Boulevard Specific Plan would implement the vision, goals, policies, and actions of the City's General Plan by establishing policies and regulations to guide subsequent development and redevelopment of the project area. There are no physical improvements or construction activites proposed by the proposed project itself, at this time. Future actions and development within the project area will be subject to additional environmental review on a project-by-project basis. Implementation of the proposed project could result in the intensification of land uses from those currently existing. The impacts of this intensification were evaluated in the General Plan EIR, which has been incorporated into this document by reference. The analysis in this MND will focus on any project-specific impacts that were not adequately addressed in the GP-EIR, and identify any impacts that may be more severe than those addressed in the GP-EIR.

Contact Information

Name
Ben Ritchie
Agency Name
City of Rancho Cordova
Contact Types
Lead/Public Agency

Location

Cities
Rancho Cordova
Counties
Sacramento
Cross Streets
Folsom Boulevard, Bradshaw Road, Sunrise Boulevard
Total Acres
9.86
Parcel #
Multiple
State Highways
50
Railways
LRT
Airports
Mather
Waterways
American River

Notice of Determination

Approving Agency
City of Rancho Cordova
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print