Forest Ranch Forest Fire Station - Facilities Replacement
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2007102096
- Lead Agency
- Forestry and Fire Protection, Department of (California Department of Forestry and Fire Protection)
- Document Title
- Forest Ranch Forest Fire Station - Facilities Replacement
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 11/21/2007
- Present Land Use
- Present Zoning is TM-5
- Document Description
- This project consists of construction of a standard CAL FIRE Two-Engine Forest Fire Station to complete the total replacement of this existing facility. The activities will be the demolition and removal of the current barracks building, construction of the prototypical 12-bed Barracks/Mess Hall Building, construction of an additional standard bay onto the existing 2-Bay Apparatus Building, and construction of prototypical Generator/Fire Pump.
- Contact Information
-
Dan Foster
California Department of Forestry and Fire Protection
P.O. Box 944246
Sacramento, CA 94244-2460
Phone : (916) 653-0839
Location
- Counties
- Butte
- Cross Streets
- State Highway 32 (5362 Platte Mountain Road)
- Zip
- 95942
- Parcel #
- 056-410-004
- State Highways
- 32
- Township
- 24N
- Range
- 3E
- Section
- 21
- Base
- MDB&M
- Other Location Info
- City/Nearest Community: Forest Ranch
Notice of Determination
- Approving Agency
- California Dept. of Forestry and Fire Protection
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- California Dept. of Forestry and Fire Protection, Sacramento Headquarters- Environmental Protection Program, PO Box 944246, 1416 9th St., Sacramento, CA 94244-2460
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- No
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.