Addendum to South Shafter Sewer, Trunk Sewer & Lift Station Project

11 Documents in Project

Summary

SCH Number
2007101148
Lead Agency
Kern County
Document Title
Addendum to South Shafter Sewer, Trunk Sewer & Lift Station Project
Document Type
NOD - Notice of Determination
Received
Posted
10/29/2019
Document Description
The MND evaluated the previous wastewater collection system for South Shafter Sewer, Truck Line Sewer & Lift Station Project. The Kern County Public Works Department (County) originally proposed to construct approximately 34,500 linear feet of sewer trunk line with associated manholes for access within existing road rights-of-way (ROW) and water line easements. The focus of this Addendum consists of comparing the original project to a modified project that reflects modifications to design elements and change in management structure that has evolved since the original approval in November 2016. Several major changes in the original project are being considered by the County, City and State Water Resources Control Board. First, some of the sewer pipeline alignments have been shifted to different road alignments after consultation with the City of Shafter’s Public Works Department; (2) instead of creating a new County Service Area Zone to oversee the wastewater collection system in the future, the City of Shafter has indicated that it proposes to assume responsibility for the collection system, with approval from the Kern County Local Agency Formation Commission of an out-of-area service contract; (3) as part of the project, the individual laterals to existing parcels will be installed to replace existing subsurface septic tanks; (4) instead of five lift stations only two lift stations will be installed; (5) instead of 386 residential parcel connections, the number of residential lots served will be 398, with the non-residential connections remaining at 10 (total 408 parcel connections to the proposed sewer system); (6) potential daily flows will be increased to an average of 152,601 gpd and a peak daily flow of 223,344 gpd; and (7) the original total length of pipeline proposed for South Shafter was estimated at 34,500 linear feet, proposed pipeline under the modified project is estimated to be about 16,500 linear feet with the same pipeline sizes.

Contact Information

Name
Patrick Waite
Agency Name
Kern County Public Works Department
Contact Types
Lead/Public Agency

Name
Agency Name
Kern County Public Works Department
Contact Types
Project Applicant

Location

Counties
Kern
Cross Streets
Shafter Ave, Poplar Ave, Beech Ave, Myrick Lane, Riverside St & Cherokee Strip
Zip
93263
State Highways
43
Railways
BNSF
Airports
Shafter-Minter Field
Schools
Golden Oak Elem
Township
28S
Range
25E
Base
MDBM
Other Information
add'l Section info: Section 16, 17, 20, 21, 22, 26 & 27

Notice of Determination

Approving Agency
Kern County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
No
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
No

Attachments

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print