CIP P2009: Jamacha Road 36-inch Potable Water Pipeline and CIP P2038: 12-inch Potable Water Pipeline Replacement

3 Documents in Project

Summary

SCH Number
2007101087
Lead Agency
Otay Water District
Document Title
CIP P2009: Jamacha Road 36-inch Potable Water Pipeline and CIP P2038: 12-inch Potable Water Pipeline Replacement
Document Type
NOD - Notice of Determination
Received
Posted
8/8/2008
Present Land Use
Transportation and School Zoning: Unzoned and School
Document Description
As outlined in the original IS/MND, CIP P2009 consists of the proposed construction of a 36-inch cement mortar lined and coated steel pipeline to transfer potable water from the San Diego County Water Authority's Otay Flor Control Facility No. 14 to the OWD Regulatory Site. CIP P2009 is approximately five miles in length and would start at the northwest corner of Lexington Avenue and Third Street in the City of El Cajon and terminate at the OWD 640-1 and 640-2 reservoirs, located at the OWD Regulatory Site at 11880 Campo Road in Rancho San Diego.

Contact Information

Name
Lisa Coburn-Boyd
Agency Name
Otay Water District
Contact Types
Lead/Public Agency

Location

Cities
El Cajon
Counties
San Diego
Cross Streets
Third St., Washington Ave., Jamacha Rd., Brabham St., Via Rancho San Diego, Fury Ln.
Zip
92019/20
Total Acres
5 linear miles
Parcel #
Linear project
State Highways
54 and 94
Schools
Cuyamaca Community College
Waterways
Sweetwater River
Township
16S
Range
1W, 1E

Notice of Determination

Approving Agency
Otay Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print