SCH Number
2007101084
Lead Agency
City of Temecula
Document Title
Ronald Reagan Sports Park Silt Removal Project
Document Type
NOD - Notice of Determination
Received
Posted
7/8/2008
Present Land Use
Public Park and Recreation/Open Space
Document Description
The California Department of Fish and Game is executing a Lake and Streambed Alteration Agreement number 1600-2007-0216-R6 pursuant to Section 1602 of the Fish and Game Code to the project applicant, City of Temecula. The applicant is proposing to remove approximately 13,700 cubic yards of silt and debris from the Ronald Reagan Sports Park Desiltation Basin as part of a routine maintenance project for the basin area. The silt that is removed from the basin area will be temporarily spread in an area adjacent to Rancho Vista Road, allowed to dry out, and then will be transported offsite to a landfill. The basin areas containing riparian vegetation impacted by maintenance activities will be allowed to reestablish between desiltation maintenance cycles.
Contact Information
Name
Anna Milloy
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Cities
Temecula
Counties
Riverside
Cross Streets
Rancho Vista Road and Margarita Road
Zip
92589
Total Acres
7.4
Parcel #
945-050-006
State Highways
SR-79, I-15
Schools
6 HS, 3 MS, 6 ES, 1 Academy, 2 Preparatory
Waterways
Temecula Creek, Murrieta Creek, Empire Creek, Long Canyon, and San Diego Aqueduct
Township
8S
Range
2W
Section
6, 7
Notice of Determination
Approving Agency
California Department of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.