Tahoe Regional Planning Agency's Updated Environmental Threshold Carrying Capacities and Regional Plan for the Lake Tahoe Basin Proposed Project

4 Documents in Project

Summary

SCH Number
2007092027
Lead Agency
Tahoe Regional Planning Agency (TRPA)
Document Title
Tahoe Regional Planning Agency's Updated Environmental Threshold Carrying Capacities and Regional Plan for the Lake Tahoe Basin Proposed Project
Document Type
NOD - Notice of Determination
Received
Posted
5/22/2013
Document Description
The project is the certification of the Lake Tahoe Water Quality Management Plant, pursuant to section 208 of the Clean Water Act (208 Plan). The 208 Plan is a framework that refers to, and describes, components of the water quality management system in the Lake Tahoe region., It was prepared by Tahoe Regional Planning Agency (TRPA), a bi-state regional planning and regulatory agency responsible for water quality management and land-use planning in the Lake Tahoe region, and must be certified by the states of Nevada and California, and approved by the U.S. EPA. To meet CEQA requirements, the Water Board relied on an EIS prepared by the Tahoe Regional Planning Agency (TRPA) for the Tahoe Regional Plan Update, pursuant to Public Resources Code section 21083.5 and section 15225 of the CEQA Guidelines.

Contact Information

Name
Kimberly Niemeyer
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
South Lake Tahoe
Counties
El Dorado, Placer
Railways
Amtrak
Airports
Tahoe
Schools
Tahoe Basin
Waterways
Lake Tahoe

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.