Candlestick Point-Hunter Point Shipyard Phase II

14 Documents in Project

Summary

SCH Number
2007082168
Lead Agency
Office of Community Investment and Infrastructure, Successor Agency to the San Francisco (OCII)
Document Title
Candlestick Point-Hunter Point Shipyard Phase II
Document Type
NOD - Notice of Determination
Received
Posted
11/20/2024
Document Description
On June 3, 2010, the San Francisco Planning Commission and the Commission for the former Redevelopment Agency of the City and County of San Francisco, acting as co-lead agencies, certified the Final Environmental Impact Report (FEIR) for the Candlestick Point-Hunters Point Shipyard Phase II Project (Project) (San Francisco Planning Department File Number 2007.0946E and San Francisco Redevelopment Agency File Number ER6.05.07). On July 13, 20l0,the San Francisco Board of Supervisors affirmed the Planning Commission's certification of the FEIR. The Project is a mixed-use development including housing, retail, office and research and development, cultural, educational, and open space uses on the approximately 702-acre site. The FEIR analyzed various Project Variants, including development of up to 5,150,000 square feet of office and research and development space. Between June 3, 2010 and August 3,2010, the Planning Commission, the former Redevelopment Agency, and the Board of Supervisors adopted environmental findings in relation to the Project, including a statement of overriding considerations and a mitigation monitoring and reporting program. On August 3, 2010, in connection with the approval of the Project, the Board of Supervisors also adopted amendments to the Bayview Hunters Point Redevelopment Plan and the Hunters Point Shipyard Redevelopment Plan (collectively, Redevelopment Plans). The Redevelopment Plans establish the land use controls for the Project. Subsequent to certification of the FEIR, the Successor Agency to the Redevelopment Agency of the City and County of San Francisco (the Office on Community Investment and Infrastructure, or OC[), in consultation with the Planning Department, prepared Addenda 1 through 7 to the FEIR analyzing certain Project modifications. OCII has adopted the Project modifications analyzed in Addenda 1,4, 5, 6, and 7; the Project modifications analyzed in Addenda 2 and 3 ultimately were not pursued or adopted.

Contact Information

Name
Jose Campos
Agency Name
Office of Community Investment and Infrastructure, Successor Agency to the San Francisco (OCII)
Job Title
Manager of Planning and Design Review
Contact Types
Lead/Public Agency

Location

Cities
San Francisco
Counties
San Francisco
Regions
Citywide, Countywide, San Francisco Bay Area
Zip
94124
Total Acres
692.6
Jobs
16316
State Highways
US101
Railways
Caltrain
Schools
Bret Harte Elementary, Malcolm X Academy, G.W. Carver Elementary
Waterways
San Francisco Bay, Yosemite Slough, Islais Creek
Other Location Info
The project is located along the southeastern waterfront of San Francisco, bordered by India Basin on the north; the Executive Park area and San Mateo County line on the south; Bayview Hill, the Bayview-Hunters Point (BVHP) neighborhood, Yosemite Slough, and Hunters Point Hill on the west; and San Francisco Bay on the north and the east. The CP site is 271.6 acres in area and is located east of Bayview Hill and southeast of the BVHP neighborhood. The HPS2 site is 421.0 acres in area and is located to the southeast of the BVHP neighborhood.

Notice of Determination

Approving Agency
Successor Agency to the San Francisco Redevelopment Agency
Approving Agency Role
Lead Agency
Approved On
County Clerk
San Francisco
Final Environmental Document Available at
https://sfocii.org/projects/hunters-point-shipyard-candlestick-point-2/document-library

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
Yes
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Attachments

Notice of Determination

Disclaimer: The Governor’s Office of Planning and Research (OPR) accepts no responsibility for the content or accessibility of these documents. To obtain an attachment in a different format, please contact the lead agency at the contact information listed above. For more information, please visit OPR’s Accessibility Site.

Download CSV New Search Print