San Rafael Rock Quarry Amended Quarry Permit and Amended Reclamation Plan

3 Documents in Project

Summary

SCH Number
2007082097
Lead Agency
Marin County
Document Title
San Rafael Rock Quarry Amended Quarry Permit and Amended Reclamation Plan
Document Type
NOD - Notice of Determination
Received
Posted
10/4/2010
Document Description
NOTE: Refer to SCH# 2005102122 The project sponsors propose to amend the existing Reclamation Plan approved for the quarry pursuant to the Surface Mining and Reclamation Act of 1975 (SMARA), (Amended Reclamation Plan ARP82 approved by the County in 1982). The proposed ARP incorporates a final grading plan, drainage system, flooding the Marin Quarry Bowl and revegetation. After completion of the mining operation, all structures, equipment and storage facilities would be removed, and the site reclaimed and revegetated in accordance with the reclamation and revegetation plan. The majoy project components of the ARP include: cutting the channel to the bay and flooding the Quarry bowl; creating three stockpile areas, stockpiling overburden and mixing pond fines into the soil in the northeast quadrant; creating a surcharge berm in the northwest quadrant; creating the South Hill soil cover; and general revegetation. As approved the reclamation plan is valid until December 31, 2024. Following termination of quarrying activities, the Quarry owner proposes to level the visual mitigation stockpiles, and flood the Quarry pit and connect it to San Francisco Bay to create a marina, suitable for commercial and residential development on the property.

Contact Information

Name
Eric Steger
Agency Name
Marin County Community Development Agency
Contact Types
Lead/Public Agency

Location

Cities
San Rafael
Counties
Marin

Notice of Determination

Approving Agency
Marin County
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.