Tehachapi Renewable Transmission Project (TRtP) Segment 7, and 8, Southern California Edison Company, Notification No. 1600-2010-0026-R5 Major Amendment 2

17 Documents in Project

Summary

SCH Number
2007081156
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Tehachapi Renewable Transmission Project (TRtP) Segment 7, and 8, Southern California Edison Company, Notification No. 1600-2010-0026-R5 Major Amendment 2
Document Type
NOD - Notice of Determination
Received
Posted
12/22/2010
Document Description
The project includes construction and operation of an 800-megawatt maximum wind energy generation facility. Major components of the project include up to 320 wind turbine generators, three or more electrical substations, meteorological towers, and one of two operations and concrete batch plants. Construction will result in 170.6 acres of permanent facilities and disturbance to an additional 378.5 acres, for a total of 549.1 acres of impacted desert tortoise (Gopherus agassizii) and Bakersfield cactus (Opuntia basilarus var. treleasei) habitat, and an additional 14.1 acres of habitat occupied by Bakersfield cactus, but not desert tortoise. The project is expected to result in the incidental take of individual desert tortoise and Bakersfield cactus, species designated respectively as threatened and endangered under the California Endangered Species Act (CESA). The Department of Fish and Game (DFG) is issuing the incidental take permit reference above as a responsible agency under the CEQA.

Contact Information

Name
Erinn WIlson
Agency Name
Department of Fish and Game South Coast Region
Contact Types
Lead/Public Agency

Location

Cities
Ontario, Tehachapi
Counties
Kern, Los Angeles, San Bernardino
State Highways
2, 14, 19, 39, 57, 60, 138
Waterways
San Gabriel River, Rio Hondo, Amargosa Creek
Other Location Info
Crosses 23 cities

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.