Arvin CSD Arsenic Mitigation Project

2 Documents in Project

Summary

SCH Number
2007081103
Lead Agency
Arvin Community Services District
Document Title
Arvin CSD Arsenic Mitigation Project
Document Type
NOD - Notice of Determination
Received
Posted
10/10/2007
Present Land Use
Zoning: M2, R-1, R-3
Document Description
The Arvin Community Services District has five wells with levels of Arsenic that do not meet the new Arsenic drinking water standard. To correct this problem, the District plans on obtaining Federal and State funds to obtain safe drinking water by one of two methods: Phase 1: would drill a test well and new wells on existing well sites to replace the old water wells with ones that produce clean water meeting Safe Drinking Water Standards. OR Phase 2: If the test well is unable to locate a clean water supply, then Phase 1 would be abandoned and Arsenic water treatment systems would be installed on the existing wells to provide clean water.

Contact Information

Name
Raymond Kincy
Agency Name
Arvin Community Services District
Contact Types
Lead/Public Agency

Location

Cities
Arvin
Counties
Kern
Cross Streets
847 S. Derby, 5th & Tejon, Monroe & Bush, 709 Charles Street, 224 Meyers Street
Zip
93203
Parcel #
192-122-08, 190-030-09, easement, 189-445-07, 191-153-08
State Highways
223
Railways
SPRR
Schools
Arvin HS, Bear Mountain ES
Waterways
Arvin Edison Canal
Township
31S
Range
29E
Section
23,26,
Base
MDB&M
Other Information
Section (con't): 36

Notice of Determination

Approving Agency
Arvin Community Services District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print