Lake Elsinore Boat Launch Facility Rehabilitation Project

2 Documents in Project

Summary

SCH Number
2007081016
Lead Agency
City of Lake Elsinore
Document Title
Lake Elsinore Boat Launch Facility Rehabilitation Project
Document Type
NOD - Notice of Determination
Received
Posted
7/7/2009
Present Land Use
General Plan: Lake Edge Specific Plan Zoning: Recreation
Document Description
CDFG is executing a Lake and Streambed Alteration Agreement (SAA # 1600-2007-0210-R6) pursuant to Section 1602 of the Fish and Game Code to the project proponent, the City of Lake Elsinore, represented by Mr. Bob Brady, City Manager. The City is proposing to restore and elevate an existing facility, and excavate or dredge a 2.2 acre boat ramp area. To construct and elevate the facility from the lake bed, the Operator proposed to place ~150,000 cubic yards of fill on the 11.5 acre site, and excavate or dredge an adjacent 2.2 acre boat ramp in the lake bed. Additional project fill material will be excavated from either a 17.5 acre, a 37.6 acre or 7.5 acre borrow site within the back basin of Lake Elsinore.

Contact Information

Name
Jeff Brandt
Agency Name
California Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
Lake Elsinore
Counties
Riverside
Cross Streets
Southwest of Riverside Drive and Lakeshore Drive
Zip
92530
Total Acres
12.6
Parcel #
379-120-008
State Highways
I-15, SR-74
Schools
Machado ES, Butterfield ES, Elsinore MS, Castle Lake ES, Terra C
Waterways
Lake Elsinore, San Jacinto River
Other Information
Schools (con't): Terra Cotta MS, Ortega HS

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.