P-PDA-06-009/Amend P-D(540) to Allow a Revised Development Plan and Development Schedule (Northpointe Shopping Center)

114 Documents in Project

Summary

SCH Number
2007072023
Lead Agency
City of Modesto
Document Title
P-PDA-06-009/Amend P-D(540) to Allow a Revised Development Plan and Development Schedule (Northpointe Shopping Center)
Document Type
NOD - Notice of Determination
Received
Posted
12/8/2009
Document Description
The proposed project would amend the development plan for P-D(540) from an 80,000 sf theatre, to a commercial development that includes a 94,000 sf building and two 7,500 sf pad buildings. The project is required to provide 367 parking spaces based on the general commercial standard of one space for every 300 sf of building area. The project will provide a total of 590 spaces. Screen landscaping will be required along the eastern property line, which is consistent with the requirement for P-D(537) to the south. The applicant has also requested a revised development schedule for P-D(540) granting an additional 10 yrs.

Contact Information

Name
David Wage
Agency Name
City of Modesto, Community & Economic Development
Contact Types
Lead/Public Agency

Location

Cities
Modesto
Counties
Stanislaus
Cross Streets
Highway 99 and Highway 132
State Highways
99, 108, 132
Railways
BNSF, UPRR, M&ET
Airports
Modesto Ci.-Co. Airport; Harry S
Waterways
Dry Creek, Tuolumne River, Stanislaus River
Other Information
Airports (Cont): Harry Sham Field

Notice of Determination

Approving Agency
City of Modesto
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.