San Luis Creek Bypass Silt Removal (ER 90-07)

3 Documents in Project

Summary

SCH Number
2007071163
Lead Agency
City of San Luis Obispo
Document Title
San Luis Creek Bypass Silt Removal (ER 90-07)
Document Type
NOD - Notice of Determination
Received
Posted
9/4/2007
Present Land Use
C/OS-20 (Conservation/Open Space with 20-acre parcel minimum)
Document Description
In 1978 the City constructed a high flow bypass channel for San Luis Obispo Creek near Los Osos Valley Road. This bypass channel allows larger flows (flows greater than a 10-year event) with an alternate path of travel than the natural stream channel. Since 1978 little maintenance has been performed on the bypass channel and the channel now has large deposits of silt and excess vegetation which do not allow the channel to perform as designed. The project will remove approximately 3,500 cubic yards of sediment and thin existing vegetation. The project area is approximately 400 feet by 70 feet (0.65 acres). The anticipated depth of silt to be removed is 3.5 feet. During the excavation, islands of vegetation will remain and after the excavation is complete the disturbed area will be seed cast in order to expedite vegetation growth. The removed silt will be trucked out of the project area outside of the flood plain. In order to remove the material, the contractor will be allowed to deposit the material on City property (25 Prado Road). The contractor will also be allowed to take the material to other locations as long as the other site is approved by the City Engineer.

Contact Information

Name
Phil Dunsmore
Agency Name
City of San Luis Obispo
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Highway 101 (12500 Los Osos Valley Road)
Zip
93401
Parcel #
053-141-013
State Highways
101
Airports
SLO County Airport
Waterways
San Luis Creek
Township
31S
Range
12E
Section
10
Base
MDB&M

Notice of Determination

Approving Agency
Community Development Director
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.