El Casco System Project (Southern Californis Edison's Title, the California Public Utilities Commission (CPCU) is the Lead Agency)

10 Documents in Project

Summary

SCH Number
2007071076
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
El Casco System Project (Southern Californis Edison's Title, the California Public Utilities Commission (CPCU) is the Lead Agency)
Document Type
EIR - Draft EIR
Received
Present Land Use
Multiple (Linear Project)
Document Description
SCE proposes to construct a new 220/115/12 kV substation (the El Casco Substation), upgrade the existing Zanja and Banning Substations and SCE's Mill Creek Communications Site, upgrade a total of 15.4 miles of 115 kV electric subtransmission line and associated structures, and install fiber optic communication cables between the Cities of Redlands and Banning. The entire project would be located within Riverside and San Bernardino Counties.

Contact Information

Name
Juralynne Mosley
Agency Name
California Public Utilities Commission
Contact Types
Lead/Public Agency

Location

Cities
Banning, Beaumont, Calimesa
Counties
Riverside, San Bernardino
Zip
Multiple
Total Acres
28 acres+ 15.4mi
Parcel #
Multiple (Linear Project)
State Highways
10, 60, 79, 243
Railways
Southern Pacific
Airports
Banning Municipal Airport
Waterways
San Timoteo Creek

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
Cal Fire, California Department of Parks and Recreation, California Department of Transportation, District 8 (DOT), California Energy Commission, California Highway Patrol, California Native American Heritage Commission (NAHC), Caltrans, Division of Aeronautics, Department of Fish and Wildlife, Region 6, Department of Toxic Substances Control, Department of Water Resources, Office of Emergency Services, California, Resources Agency, State Water Resources Control Board, Division of Water Quality
Development Types
Power:Electric Transmission Lines (Sub-T/L & substation)(Megawatts 115 kV)
Project Issues
Cumulative Effects, Noise, Alternatives

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print