Temporary Recycled Water Irrigation Project

2 Documents in Project

Summary

SCH Number
2007062058
Lead Agency
Rancho Murieta Community Services District
Document Title
Temporary Recycled Water Irrigation Project
Document Type
NOD - Notice of Determination
Received
Posted
7/31/2007
Present Land Use
Permanent Agricultural Extensive Land Use Zone AG-80 / General Agriculture
Document Description
The project is the proposed Rancho Murieta Community Services District Temporary Recycled Water Irrigation Project. The project consists of installing new temporary above-ground reclaimed water conveyance pipelines to deliver recycled water to grazing pastures on land south of the wastewater treatment plant. The District would have easement rights to use the lands by acquiring a non-exclusive irrigation easement on the property that would end no later than December 31, 2009. The project would be used to meet the Central Valley Regional Water Quality Board's Cease and Desist Order No. R5-2006-0001 to dispose of approximately 300 acre feet of carry over treated wastewater that was not delivered to the Rancho Murieta Country Club.

Contact Information

Name
Edward Crouse
Agency Name
Rancho Murieta Community Services District
Contact Types
Lead/Public Agency

Location

Cities
Rancho Murieta
Counties
Sacramento
Cross Streets
SR-16
Zip
95683
Total Acres
97
Parcel #
128-0080-07, 128-0080-068
State Highways
16
Airports
Van Vleck Airstrip
Waterways
Cosumnes River, Arkansas Creek

Notice of Determination

Approving Agency
Rancho Murieta Community Services District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print