Natomas Levee Improvement Program (NLIP) Natomas Cross Canal (NCC) Landside Improvements Project
31 Documents in Project
Summary
SCH Number
2007062016
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Natomas Levee Improvement Program (NLIP) Natomas Cross Canal (NCC) Landside Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
5/1/2008
Present Land Use
Agricultural, Residential, Light Industrial, Industrial Office Park, and Industrial/Commercial Reserve
Document Description
The Phase 1 improvements involve constructing a cutoff wall in the westerly 12,500' of the NCC south levee to address through- and under-seepage concerns. The Phase 2 improvements involve raising the NCC south levee to provide additional freeboard; realigning the levee to provide a more stable waterside slope and to reduce the need to remove waterside vegetation; and constructing a cutoff wall in the eastern ~4.3 miles of the levee to reduce the risk of levee failure.
Contact Information
Name
George Qualley
Agency Name
Dept. of Water Resources
Contact Types
Lead/Public Agency
Phone
Location
Cities
Sacramento
Counties
Sacramento
Cross Streets
Numerous
Total Acres
53,000
State Highways
I-5, SR 99, SR 70, I-80
Airports
Sacramento International
Waterways
Sacramento and American Rivers, Natomas Cross Canal, Natomas East Main Drainage Canal
Other Location Info
City/Nearest Community: Natomas Basin
Notice of Determination
Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes