Natomas Levee Improvement Program (NLIP) Natomas Cross Canal (NCC) Landside Improvements Project

28 Documents in Project

Summary

SCH Number
2007062016
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Natomas Levee Improvement Program (NLIP) Natomas Cross Canal (NCC) Landside Improvements Project
Document Type
NOD - Notice of Determination
Received
Posted
5/1/2008
Present Land Use
Agricultural, Residential, Light Industrial, Industrial Office Park, and Industrial/Commercial Reserve
Document Description
The Phase 1 improvements involve constructing a cutoff wall in the westerly 12,500' of the NCC south levee to address through- and under-seepage concerns. The Phase 2 improvements involve raising the NCC south levee to provide additional freeboard; realigning the levee to provide a more stable waterside slope and to reduce the need to remove waterside vegetation; and constructing a cutoff wall in the eastern ~4.3 miles of the levee to reduce the risk of levee failure.

Contact Information

Name
George Qualley
Agency Name
Dept. of Water Resources
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Counties
Sacramento
Cross Streets
Numerous
Total Acres
53,000
State Highways
I-5, SR 99, SR 70, I-80
Airports
Sacramento International
Waterways
Sacramento and American Rivers, Natomas Cross Canal, Natomas East Main Drainage Canal
Other Location Info
City/Nearest Community: Natomas Basin

Notice of Determination

Approving Agency
DWR
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print