Rio Dell Treated Wastewater Reuse Project

14 Documents in Project

Summary

SCH Number
2007062006
Lead Agency
City of Rio Dell
Document Title
Rio Dell Treated Wastewater Reuse Project
Document Type
NOD - Notice of Determination
Received
Posted
6/8/2009
Document Description
The City is now pusuing American Recovery and Reinvestment Act funding through the State Water REsources Control Board Clean Water State Revolving Fund Program to temporarily install some of the equipment approved for the new treatment facility at the existing Wastewater Treatment Plant (WWTP), until the new treatment facility is constructed. The new treatment facility is expected to be constructed by 2011. The improvements to be constructed and operated at the existing WWTP would include the following: Installation and operation of a skid-mounted mechanical biosolids dewatering device and covered biosolids storage building; and Installation and operation of a skid-mounted sodium dioxide generator with a 500 gallon brine tank and 2,500 gallon sodium hypochlorite storage tank to replace the existing gaseous chlorine disinfection system. The equipment would be installed in such as manner as to avoid the adjacent tree. Each piece of equipment would be installed with a containment system sized to hold all the material stored therein, in case of a leak. An Addendum to the EIR was prepared to analyze changes to the adopted project that are required to temporarily install and operate this equipment. This June 2009 Addendum concludes that the changes tot he adopted project being proposed do not cause substantial changes in impacts analyzed for the proposed project in the 2008 Certified EIR and do no result in new significant impacts.

Contact Information

Name
Nancy Flemming
Agency Name
City of Rio Dell
Contact Types
Lead/Public Agency

Location

Cities
Rio Dell
Counties
Humboldt
Cross Streets
Highway 101
Zip
95562
Parcel #
Multiple
State Highways
101
Railways
Northern Pacific Railroad
Waterways
Eel River
Township
1N, 2N
Range
1E, 1W
Section
Many
Base
HB&M

Notice of Determination

Approving Agency
City of Rio Dell
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.