Emblem Elementary School Two-Story Classroom Addition

2 Documents in Project

Summary

SCH Number
2007051060
Lead Agency
Saugus Union School District
Document Title
Emblem Elementary School Two-Story Classroom Addition
Document Type
NOD - Notice of Determination
Received
Posted
6/22/2007
Present Land Use
Public School Zoning: Residential-Suburban General Plan: P
Document Description
The project, as proposed, will involve the construction of a two-story addition to the school, whereby 15 relocatable classrooms will be replaced with 16 new classrooms. Construction if this site will require the grading of approx. 1 acre. The project will increase student capacity, as compared to that remaining after the above referenced modernization and construction, to 811 students. The project will also involve minor improvements to the school playground, including improvements on the irrigation and field turf and the installation of a backstop, as well as the addition of approx. 800 sq. ft. outdoor stage outside the multi-purpose room and a covered entry to the administrative buildings. The project will also include low level walkway lighting in the vicinity of the newly constructed two story classroom structure.

Contact Information

Name
Harold Pierre
Agency Name
Saugus Union School District
Contact Types
Lead/Public Agency

Location

Cities
Santa Clarita
Counties
Los Angeles
Cross Streets
Espuella Drive and Bouquet Canyon Road
Zip
91350
Total Acres
9.88
Parcel #
2849-018-900
State Highways
126
Railways
UPRR
Schools
Saugus HS, Santa Clarita ES
Waterways
Santa Clara River, Bouquet Canyon Creek
Township
4N
Range
16W
Base
SB

Notice of Determination

Approving Agency
Board of Trustees of the Saugus Union School District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print