Lewiston-Dark Gulch Rehabilitation Project: Trinity River Mile 105.4 to 111.7
5 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2007042161
- Lead Agency
- Trinity County Resource Conservation District
- Document Title
- Lewiston-Dark Gulch Rehabilitation Project: Trinity River Mile 105.4 to 111.7
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 2/21/2008
- Present Land Use
- Rural Residential, Commercial, Open Space, Flood Hazard, and Village
- Document Description
- This project would implement important provisions of the Interior Secretary's December 19, 2000 Record of Decision (ROD) for Trinity River Restoration. Construction will create additional fish and wildlife habitat that is expected to increase over time as river processes are restored. Work to be performed includes re-contouring bank and floodplain features, as well as conducting in-river work such as gravel placement and grade control removal.
- Contact Information
-
Alex Cousins
Trinity County Resource Conservation District
Lead/Public Agency
1 Horseshoe Lane P.O. Box 1450
Weaverville, CA 96093
Phone : (530) 623-6004
Location
- Counties
- Trinity
- Cross Streets
- Highway 299
- Parcel #
- Multiple
- State Highways
- 299
- Schools
- Lewiston Elementary
- Waterways
- Trinity River
- Base
- MDB&M
- Other Location Info
- City/Nearest Community: Lewiston
Notice of Determination
- Approving Agency
- Trinity County Resource Conservation District
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- Trinity County Resource Conservation District, Trinity River Restoration Program, and Trinity County Library-Weaverville Branch
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.