San Ramon City Center Project

12 Documents in Project

Summary

SCH Number
2007042022
Lead Agency
San Ramon, City of (City of San Ramon)
Document Title
San Ramon City Center Project
Document Type
NOD - Notice of Determination
Received
Posted
12/13/2007
Present Land Use
Mixed use; City Center Mixed Use

Document Description
The proposed project consists of the new construction of approx. 2.1 million sq. ft. of retail, hotel, residential, office, and civic uses on approx. 44 acres. As part of the project, 194,652 sq. ft. of existing office space will be demolished, and the project will utilize a vested un-built office entitlement of 328,220 sq. ft. As a result, the project would result in a net increase of 1.6 million sq. ft. above the existing vested entitlements for the site. Specific project elements include approx.: 635,000 sq. ft. of retail and cinema uses, a 169 room hotel, up to 487 residential dwelling units, 680,000 sf of office space, 50,000 sf of retail/ flex uses, and a 110,000 sf City Hall, including Council Chambers, Library, and Police Dept. Headquarters.

Contact Information
Lauren Barr
City of San Ramon
2222 Camino Ramon
San Ramon, CA 94583

Phone : (925) 973-2567

Location

Cities
San Ramon
Counties
Contra Costa
Cross Streets
Bollinger Canyon Road and Camino Ramon, Sunset Drive, Bishop Drive
Zip
94583
Total Acres
43.65
Parcel #
213-120-009, 013; 213-133-063, 086
State Highways
I-680
Schools
Iron Horse MS
Waterways
South San Ramon Creek
Township
2S
Range
1W
Section
30
Base
MDB&M

Notice of Determination

Approving Agency
City of San Ramon
Approving Agency Role
Lead Agency
Approved On
Final Environmental Document Available at
City of San Ramon, Planning/Community Development Dept., 2222 Camino Ramon, San Ramon, CA 94583

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print