Public Works- Cypress Mountian Drive Bridge Repair Project; ED06-271 (245R12B501)
2 Documents in Project
Summary
SCH Number
2007031154
Lead Agency
San Luis Obispo County
Document Title
Public Works- Cypress Mountian Drive Bridge Repair Project; ED06-271 (245R12B501)
Document Type
NOD - Notice of Determination
Received
Posted
9/7/2007
Present Land Use
Agriculture, Rural Lands
Document Description
The California Dept. of Fish and Game is executing a Lake and Streambed ALteration Agreement pursuant to Section 1602 of the Fish and Game Code to the project applicant, County of San Luis Obispo Public Works Dept. The project consists of replacement and reinforcement of bridge footings, construction of a new scour protection wall, and replacement of support posts at the Cypress Mountain Drive Bridge over Las Tablas Creek. A temporary ramp will be cut to the creek bed to allow equipment access into the creek bed. Following construction, the streambed and temporary ramp area will be restored to their original contours, and streambanks stabilized and revegetated with native species.
Contact Information
Name
Julie Means
Agency Name
California Dept. of Fish and Game
Contact Types
Lead/Public Agency
Phone
Location
Counties
San Luis Obispo
Cross Streets
Cypress Mountain Drive and Klau Mine Road
Zip
93465
Total Acres
0.1
Waterways
Las Tablas Creek
Township
26S
Range
10E
Section
33
Base
MD
Other Location Info
City/ Nearest Community: Cayucos
Notice of Determination
Approving Agency
California Dept. of Fish and Game
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.