Granite Construction Company Twentynine Palms Mine Expansion and Reclamation Plan

6 Documents in Project

Summary

SCH Number
2007031146
Lead Agency
City of Twentynine Palms
Document Title
Granite Construction Company Twentynine Palms Mine Expansion and Reclamation Plan
Document Type
NOD - Notice of Determination
Received
Posted
8/12/2010
Document Description
The City has approved a project by Granite Construction Company to utilize 178 acres of the 356 acre project site for incremental phased sand, gravel and aggregate mining at an estimated rate of 332,000 cy (450,000 net tons) per year for 86 yrs. The average mining depth would be 100 ft below ground surface. Upon completion of mining activity, the total excavation area would ultimately occupy 291.5 acres (including 113.5 acres on an existing mining operation). The remaining 178 acre of the 356 acre project site will be undisturbed and left as open space for habitat for the desert tortoise and other threatened or endangered species. The mine expansion area and the existing mining site (a total acreage of 469.5 acres) will be reclaimed pursuant to a reclamation plan.

Contact Information

Name
Charles La Claire
Agency Name
City of Twentynine Palms Community Development Dept
Contact Types
Lead/Public Agency

Location

Cities
Twentynine Palms
Counties
San Bernardino
Cross Streets
Twentynine Palms Highway (Highway 62)
Zip
92277
Total Acres
356
Parcel #
591-301-004 005; 591-341-001, 006, 007, 008
State Highways
62
Waterways
No
Township
1S
Range
9E
Section
1, 6
Base
SBB&M

Notice of Determination

Approving Agency
Twentynine Palms City
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.