Anaheim Bay Bridge Rock Slope Protection and Drainage Maintenance Plan

2 Documents in Project

Summary

SCH Number
2007031105
Lead Agency
Regional Water Quality Control Board, Region 8 (Santa Ana), Riverside
Document Title
Anaheim Bay Bridge Rock Slope Protection and Drainage Maintenance Plan
Document Type
NOD - Notice of Determination
Received
Posted
5/14/2007
Present Land Use
Caltrans right-of-way for the Pacific Coast Highway.
Document Description
The project is for the reconstruction of the northeast abutments and roadway embankments of the Anaheim Bay Bridge. The reconstruction is a project by Caltrans, and includes the following: Bridge abutments and embankments will be constructed to a 1.5:1 slope. Erosion control blanket will be placed up to the top of the slope and 2 metal beam guard rail ends will be replaced. New chain link fence will be installed, a maintenance vehicles pull-out will be constructed, existing storm drain pipes will be lined, 4 new storm drain inlets will be constructed, 7 outfalls will be reconstructed along with new rip-rap energy dissipation.

Contact Information

Name
Adam Fischer
Agency Name
Santa Ana Regional Water Quality Control Board
Contact Types
Lead/Public Agency

Location

Cities
Seal Beach
Counties
Orange
Cross Streets
Pacific Coast Highway at Anaheim Bay
Zip
90740
Total Acres
4.2
State Highways
1
Airports
Seal Beach NWS
Schools
McGaugh and Zoetzer
Waterways
Anaheim Bay
Township
5S
Range
12W
Base
Seal Bea
Other Information
Base: Seal Beach

Notice of Determination

Approving Agency
Santa Ana Regional Water Quality Board
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.