UCLA Spieker Aquatic Center

2 Documents in Project

Summary

SCH Number
2007031020
Lead Agency
University of California, Los Angeles
Document Title
UCLA Spieker Aquatic Center
Document Type
NOD - Notice of Determination
Received
Posted
7/20/2007
Present Land Use
Campus Recreation and Housing
Document Description
The project includes construction of a competition swimming pool and related facilities at the Sunset Canyon Recreation Center in the northwest zone of the UCLA campus. The Spieker Aquatic Center will be designed to support the swimming, water polo and diving programs of the Departments of Intercollegiate Athletics and Cultural and Recreational Affairs, and will meet the design standards governing competitive collegiate aquatic sports. Project components include the new 52-meter deep-water pool, an approximately 6,000 square foot support facility, dive tower, lighting, scoreboard, space to accommodate temporary spectator seating for special aquatics and tennis events, and landscape elements. In order to create a site for the aquatic center, the project would displace two existing tennis courts, and six mini-basketball courts. The project includes replacement of the basketball and tennis functions at other locations in the Northwest and Central zones of the campus.

Contact Information

Name
John E. Zimmermann
Agency Name
University of California
Contact Types
Lead/Public Agency

Location

Cities
Los Angeles, Los Angeles, City of
Counties
Los Angeles
Cross Streets
Sunset Boulevard and Bellagio Drive
Zip
90024
State Highways
I-405
Other Location Info
West Los Angeles

Notice of Determination

Approving Agency
University of California
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print