Carmichael Water District Planned System Maintenance Pipeline Replacement Project SAA 1600-2010-0033

4 Documents in Project

Summary

SCH Number
2007022100
Lead Agency
Carmichael Water District
Document Title
Carmichael Water District Planned System Maintenance Pipeline Replacement Project SAA 1600-2010-0033
Document Type
NOD - Notice of Determination
Received
Posted
7/12/2010
Document Description
The project is limited to the replacement of an 18 inch welded steel pipeline that provides irrigation and domestic water service to the Park and Golf Course. The project will include the construction of a new ductile iron pipeline in Tarshes Drive from California Avenue to Ancil Hoffman Park Golf Course, irrigation pump station facility. The pipeline will cross Carmichael Creek in two locations. The pipeline crossings of the creek will be installed via open cut excavation during the summer months when the creek is dry. The approximate volume of concrete to encase the pipeline is 1,2154 cf (45 cy) with ~135 linear ft of ductile iron pipe crossing the creek (70 ft at Xing 1 and 65 ft at Xing 2). The remaining pipeline trench will be backfilled with native material compacted to 90%.

Contact Information

Name
Amy Kennedy
Agency Name
Department of Fish and Game
Contact Types
Lead/Public Agency

Location

Counties
Sacramento
Cross Streets
California Avenue and Tarshes Drive
Zip
95608
Total Acres
0.75
Schools
Carmichael ES
Waterways
Carmichael Creek, American River
Township
9N
Range
6E
Section
Unsect
Base
MD
Other Location Info
City/Nearest Community: Carmichael

Notice of Determination

Approving Agency
Deaprtment of Fish and Game
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.