Power Line-Elkhorn Substation Capacity Expansion Project

4 Documents in Project

Summary

SCH Number
2007022043
Lead Agency
Sacramento Municipal Utility District
Document Title
Power Line-Elkhorn Substation Capacity Expansion Project
Document Type
MND - Mitigated Negative Declaration
Received
Present Land Use
The substation capacity expansion site would be located on land designated Public Facilities and zoned AG-80.
Document Description
The proposed Power Line-Elkhorn substation capacity expansion project would increase the footprint of the Power Line-Elkhorn substation by approximately 0.5 acre (from approximately 0.62 acre to approximately 1.12 acres). The proposed project would replace a 3.75 mega volt-amperes (MVA) transformer with a 25 MVA transformer, and a 12.5 MVA transformer with a 25 MVA transformer, thus increasing the capacity of the substation from 16.25 to 50 MVA. Additional improvements include a 69,000-volt (69-kV) bus structure and three 69-kV circuit breakers, new switchgear, new cement slabs for the equipment and grounding, and fencing to encompass the footprint of the substation. The existing 69-kV pole line would remain. Reconductoring would occur to increase ampacity for the capacity increase. Additionally, five new 12,000-volt (12-kV) feeders would be added (totaling eight 12-kV feeders), and the existing 69-kV pole arrangement to the transformers would be replaced. The existing substation site is connected to the Elverta Circuit #1 and the Natomas Circuit #2 existing overhead (69-kV) lines with SMUD's subtransmission grid system.

Contact Information

Name
Ron Scott
Agency Name
Sacramento Municipal Utility District
Contact Types
Lead/Public Agency

Location

Counties
Sacramento
Cross Streets
Power Line Road and Elkhorn Boulevard
Zip
95835
Total Acres
1.12
Parcel #
201-0230-036-0000, 045-0000
State Highways
SR 70/00, I-5
Airports
Sacramento International Airport
Waterways
Unnamed drainage 370 feet west of the site; RD 1000 drainage canal along Power Line Road
Township
10N
Range
4E
Section
30
Base
MDBM
Other Location Info
City/Nearest Community: North Natomas

Notice of Completion

State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, North Central Region 2 (CDFW), California Department of Health Care Services (DHCS), California Department of Parks and Recreation, California Department of Transportation, District 3 (DOT), California Energy Commission, California Highway Patrol, California Native American Heritage Commission (NAHC), California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, Central Valley Sacramento Region 5 (RWQCB), Resources Agency, Department of Water Resources
State Reviewing Agency Comments
Department of Water Resources
Development Types
Power:Other Power Type (Electrical Substation)
Local Actions
SMUD Board Adoption
Project Issues
Aesthetics, Agriculture and Forestry Resources, Air Quality, Biological Resources, Cultural Resources, Cumulative Effects, Drainage/Absorption, Flood Plain/Flooding, Geology/Soils, Growth Inducement, Hazards & Hazardous Materials, Hydrology/Water Quality, Land Use/Planning, Mineral Resources, Noise, Public Services, Recreation, Schools/Universities, Solid Waste, Transportation, Vegetation, Wetland/Riparian, Wildlife

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print