Copco Road at Jenny Creek Bridge Replacement Project

3 Documents in Project

Summary

SCH Number
2007022037
Lead Agency
Siskiyou County
Document Title
Copco Road at Jenny Creek Bridge Replacement Project
Document Type
NOD - Notice of Determination
Received
Posted
3/16/2007
Present Land Use
AG-2-B-80 (Non-Prime Ag. Dist., Combining District Lands, min 80-ac parcel size); AG-2-B-40 (Non-Prime Ag. Dist., Combining District Lands, min 40-ac parcel size).
Document Description
Siskiyou County proposes to replace the existing bridge (02C-061) on Copco Road over Jenny Creek. The purpose of the project is to replace the existing structurally deficient timber bridge with a new bridge that will provide safer travel for the traveling public and meet minimum recommended standards of Caltrans and FHWA. The new proposed bridge will be a single-span, concrete structure on sixteen piles. It will sit within the existing right of way and will be 24 feet wide and 109 feet in length, on two abutments; there will be no center pier. The new bridge will be placed in the same location as the existing bridge. A detour will be established using the old road that loops around the existing bridge to the north. The detour will require the installation of an 80-foot temporary bridge across Jenny Creek. A contractor's staging area will be a turnout along Copco Road, just east of Jenny Creek.

Contact Information

Name
Scott Waite
Agency Name
Siskiyou County Planning Department
Contact Types
Lead/Public Agency

Location

Counties
Siskiyou
Cross Streets
Copco Road at Jenny Creek
Zip
96097
Total Acres
4.26
Parcel #
041-030-230
Waterways
Jenny Creek, Iron Gate Reservoir
Township
48N
Range
5W
Section
26, 35
Base
MDBM
Other Location Info
City/Nearest Community: Copco

Notice of Determination

Approving Agency
Siskiyou County Department of Public Works
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.