City of San Joaquin Wastewater Treatment Plant Expansion Project (Project); SCWG Project No.: SCWG-912

3 Documents in Project

Summary

SCH Number
2007021091
Lead Agency
City of San Joaquin
Document Title
City of San Joaquin Wastewater Treatment Plant Expansion Project (Project); SCWG Project No.: SCWG-912
Document Type
NOD - Notice of Determination
Received
Posted
9/6/2007
Present Land Use
Treatment Plant - Wastewater Treatment Plant, Expansion Area - Agriculture
Document Description
The proposed project will upgrade and expand the wastewater treatment plant to meet the Central Valley Regional Water Quality Control Board Cease and Desist Order. The proposed project will increase the treatment plant and pumping station capacity from 0.252 million-gallons per day to 0.5 million-gallons per day. The City intends to construct a new extended aeration biological treatment process to replace the existing mechanical surface aerated pond system. The City will convert the aeration basin and two sedimentation ponds into evaporation/percolated ponds. For the added percolation capability, the City will construct a new lift station with two 800 gallons per minute pumps, and add a 12-inch forcemain parallel to the existing eight-inch forcemain to accommodate increased flows.

Contact Information

Name
Michelle L. Jones
Agency Name
State Water Resource Control Board
Contact Types
Lead/Public Agency

Location

Cities
San Joaquin
Counties
Fresno
Cross Streets
Manning Avenue
Total Acres
75
Parcel #
030-100-046, 036P
State Highways
Hwy. 145
Waterways
Fresno Slough
Township
15S
Range
16E
Section
27
Base
MD

Notice of Determination

Approving Agency
State Water Resource Control Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.