Imperial Irrigation District's El Centro Unit 3 Repower Project

2 Documents in Project

Summary

SCH Number
2007019017
Lead Agency
California Energy Commission
Document Title
Imperial Irrigation District's El Centro Unit 3 Repower Project
Document Type
NOD - Notice of Determination
Received
Posted
1/24/2007
Present Land Use
City Zoning Ordinance: The project site is currently zoned Limited Use (LU) County Zoning Ordinance: Agriculture (A2 and A2U) and Manufacturing Light Industrial
Document Description
IID proposes to replace an existing boiler with a General Electric Frame 7EA dry low NOx combustion turbine generator within the site of the existing El Centro Generating Station (ECGS) in El Centro, Imperial County, California. Most of the existing Unit 3 plant systems will continue to be used with only minor modifications. The Unit 3 repower will increase the existing Unit 3 generating capacity by 84 megawatts (MW) from 44 MW to 128 MW. The El Centro Unit 3 Repower Project would be owned and operated by IID. It will continue to serve the growing electrical load demands of the region.

Contact Information

Name
Mary Dyas
Agency Name
California Energy Commission
Contact Types
Lead/Public Agency

Location

Cities
El Centro
Counties
Imperial
Cross Streets
East Villa Avenue and North Dogwood Road
Zip
92243
Parcel #
044-430-008, 009, 010 and 011
State Highways
I-8
Railways
SPRR
Schools
Washington Elementary School

Notice of Determination

Approving Agency
California Energy Commission
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.