178 Townsend Project
2 Documents in Project
Summary
SCH Number
2007012109
Lead Agency
City and County of San Francisco
Document Title
178 Townsend Project
Document Type
EIR - Draft EIR
Received
Present Land Use
The site is zoned SLI (Service/Light Industrial)
Document Description
The project site at 176 Townsend Street is occupied by the California Electric Light Company Station B building, a contributory building within the South End Historic District. The Project Sponsor proposes to rehabilitate and convert the building from its current use as a valet parking garage to a residential use with up to 85 housing units and accessory off-street parking for the residential uses. The proposed project also includes ground-floor retail uses. The proposed uses would be housed in a five-story building that would be constructed within the footprint of the existing building on the site, totaling approximately 98,900 gross square feet (gsf), with up to 71,500 gsf in residential uses and up to 1,050 gsf in retail uses as well as parking space, open space, common area, and building service space. New construction would include a partially below-grade parking garage, a five-story structure containing the residential and retail components, and street improvements along Clarence Place. The proposed new structure would be contained within the walls of the existing historic structure and would be set back 40 feet from the Townsend Street facade. The new building would rise above the historic structure's existing 23 to 42 foot tall roofline to a maximum height of 50 feet. The ground-floor level would include an enclosed entry courtyard accessible from the Townsend Street entrance, leading to a central hallway connecting to three smaller internal courtyards that would be open to the floors above. Approximately 5,373 gsf of common usable open space would be provided in the entry courtyard and a roof-top deck. Balconies would provide an additional 3,754 gsf of private open space for 38 of up to 85 proposed units. A one-level, 13,200-gsf, partially underground parking garage would include 74 parking spaces for use by the projects residents, with 72 spaces provided by two-car stackers, as well as 33 bicycle parking spaces in stacked lockers. The garage would be accessed through an existing opening in the facade on Clarence Place.
Contact Information
Name
Sarah Jones
Agency Name
City and County of San Francisco Planning Department
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Francisco
Counties
San Francisco
Cross Streets
On the corner of Townsend Street and Clarence Place between 2nd and 3rd Streets
Zip
94612
Total Acres
0.5
Parcel #
Block 3788, Lot 012
State Highways
80, 280, 101
Railways
Caltrain
Waterways
San Francisco Bay
Notice of Completion
State Review Period Start
State Review Period End
State Reviewing Agencies
California Department of Fish and Wildlife, Bay Delta Region 3 (CDFW), California Department of Parks and Recreation, California Department of Transportation, District 4 (DOT), California Highway Patrol, California Native American Heritage Commission (NAHC), California Public Utilities Commission (CPUC), California Regional Water Quality Control Board, San Francisco Bay Region 2 (RWQCB), Department of Water Resources, Resources Agency, Department of Toxic Substances Control
State Reviewing Agency Comments
Department of Toxic Substances Control
Development Types
Residential (Units 85), Commercial (Sq. Ft. 1,050), Other (Parking,loading,storage;common area, circulation,building serv.,)
Local Actions
Use Permit
Project Issues
Cultural Resources, Land Use/Planning, Transportation