Concurrence in the issuance of a revised Solid Waste Facilities Permit (SWFP 01-Aa-0290) for the Alameda County Industires Transfer/Processing Facility
3 Documents in Project
Summary
SCH Number
2007012055
Lead Agency
City of San Leandro
Document Title
Concurrence in the issuance of a revised Solid Waste Facilities Permit (SWFP 01-Aa-0290) for the Alameda County Industires Transfer/Processing Facility
Document Type
NOD - Notice of Determination
Received
Posted
7/19/2007
Present Land Use
Z: IG Industrial General
GP: Public/Institutional
Document Description
The proposed new permit is to allow the following: The combining of the acreage and capacity of the pre-existing recycling center and direct transfer station into one permitted facility with an increase in tonnage; 412 ton per day maximum; 193 vehicle trips per day maximum. Waste Types: Non-hazrdous municipal solid wastes. Proposed Hours of Operation: Transfer/Processing Facility: 5:00 a.m. to 3:30 p.m., Direct transfer activities only from 5:00 a.m. to 5:00 p.m.
Contact Information
Name
Reinhard Hohlwein
Agency Name
California Integrated Waste Management Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
San Leandro
Counties
Alameda
Cross Streets
Alvarado Street; project site at dead-end of Aladdin (610 Aladdin Avenue)
Zip
94577
Total Acres
2.82
Parcel #
77B-800-15
State Highways
61, 112, 580, 880, 185
Railways
UPRR
Schools
San Leandro Unified
Waterways
San Leandro Creek, San Lorenzo Creek, Co. Flood Control Channel
Notice of Determination
Approving Agency
California Integrated Waste Management
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
N/A