Balboa Marina Dock Replacement

3 Documents in Project

Summary

SCH Number
2007011017
Lead Agency
City of Newport Beach
Document Title
Balboa Marina Dock Replacement
Document Type
NOD - Notice of Determination
Received
Posted
2/16/2007
Present Land Use
The General Plan and Local Coastal Program Land Use Plan designation for the project site is Recreational Marine Commercial. The project site is developed with a 132 slip marina facility.
Document Description
The project proposes to replace an existing 132 slip, 27,550 sq. ft. dock with a 20,483 sq. ft. dock to accommodate 102 slips ranging from 22 to 58 feet in length. The proposed floating dock would be constructed of concrete and consist of 5 to 6 foot wide slip fingers and an 8-foot wide walkway. The reconstruction will include the installation of new lighting, electrical power connections, water supply lines, communication hook-ups, a pump-out station and fire fighting facilities. The design also incorporates accommodation for on-site mitigation of impacts to eelgrass associated with the reconstruction.

Contact Information

Name
Tom Rossmiller
Agency Name
City of Newport Beach
Contact Types
Lead/Public Agency

Location

Cities
Newport Beach
Counties
Orange
Cross Streets
East Coast Highway and Bayside Drive
Total Acres
~ 2.74 (water)
State Highways
Highway 1 (PCH)
Schools
Mariners and Our Lady Queen of Angels ES; Corona Del Mar and New
Waterways
Pacific Ocean, Newport Bay
Other Information
Schools: Newport Harbor HS

Notice of Determination

Approving Agency
City of Newport Beach
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.