Avenue 40 Well Site (Talavera Off-site Well No. 1) Project

2 Documents in Project

Summary

SCH Number
2006121102
Lead Agency
Coachella Valley Water District (CVWD)
Document Title
Avenue 40 Well Site (Talavera Off-site Well No. 1) Project
Document Type
NOD - Notice of Determination
Received
Posted
2/21/2007
Present Land Use
Light Agricultural GP: Light Agricultural
Document Description
This project includes the drilling, testing, casing, and development of a domestic water well, and installing of approximately 300 feet of 12-inch ductile iron pipe. The pipeline portion of this project includes installation of a pipeline at the well site, which is located south of Avenue 40 on the east side of Taylor Place. The pipeline will extend north and enter Avenue 40 and tie into an existing 18-inch CVWD water main north of the Avenue 40 centerline. The existing line continues west to Adams Street. The well portion of the project includes the construction of a well site that contains a 300 horsepower motor, 2,000 gallon per minute pump and other appurtenances. The well and pumping plant will be incorporated into the existing domestic water system.

Contact Information

Name
Luke Stowe
Agency Name
Coachella Valley Water District
Contact Types
Lead/Public Agency

Location

Cities
Indio
Counties
Riverside
Cross Streets
Taylor Place / Avenue 40
Zip
92203
Total Acres
0.75
Parcel #
607-230-018
State Highways
I-10
Railways
UPRR
Airports
Thermal Airport
Waterways
Coachella Valley Stormwater Channel; Coachella Canal
Township
5S
Range
7E
Section
8
Base
SB

Notice of Determination

Approving Agency
Board of Directors of the Coachella Valley Water District
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.