New Crystal Springs Bypass Tunnel Project

5 Documents in Project

Summary

SCH Number
2006112077
Lead Agency
City and County of San Francisco
Document Title
New Crystal Springs Bypass Tunnel Project
Document Type
NOD - Notice of Determination
Received
Posted
7/29/2008
Present Land Use
Open Space, pipe storage, and valve vaults/RM-Resource Management
Document Description
The New Crystal Springs Bypass Tunnel Project consists of the construction of a tunnel, about 4,200 feet long with a 96-inch diameter pipeline in the tunnel for conveyance of drinking water to the regional water delivery system in San Mateo County and San Francisco. This project would be located in the SFPUC right-of-way along and near Polhemus and Crystal Springs Roads in San Mateo County. The tunnel would replace an existing pipeline that is subject to geologic hazards from slope instability. Construction of the project is scheduled to begin toward the end of 2008 and work is anticipated to continue through 2011.

Contact Information

Name
Susan Mickelsen
Agency Name
San Francisco Planning Department
Contact Types
Lead/Public Agency

Location

Cities
Hillsborough
Counties
San Mateo
Cross Streets
Polhemus Road and Crystal Springs Road
Zip
94402
Parcel #
09314103,093070050
State Highways
92
Schools
Serra High, Highlands Elementary, Odyssey School
Waterways
Polhemus Creek, San Mateo Creek
Township
5S
Range
4W
Base
MDB&M

Notice of Determination

Approving Agency
City and County of San Francisco
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
N/A

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.