North Connector Project

4 Documents in Project

Summary

SCH Number
2006112062
Lead Agency
Solano Transportation Authority
Document Title
North Connector Project
Document Type
NOD - Notice of Determination
Received
Posted
5/16/2008
Present Land Use
Commercial, agricultural, and residential Zoning: commercial, agricultural, and residential General Plan: commercial, agricultural, and residential
Document Description
Then North Connector Project, located primarily in unincorporated Solano County near the City of Fairfield, involves the construction of two sections of roadway (the East End and West End) to provide additional east-west capacity north of U.S. I-80 for local traffic, which currently uses U.S. I-80. The project will be a total of 3.7 linear miles (including both the East and West End components). Existing land uses in the project area are comprised mostly of agricultural uses, as well as some residential and commercial development.

Contact Information

Name
Janet Adams
Agency Name
Solano Transportation Authority
Contact Types
Lead/Public Agency

Location

Cities
Fairfield
Counties
Solano
Cross Streets
U.S. I-80 at SR 12 West/Red Top Road (West End) to U.S. I-80 at Chadbourne Road (East End)
Zip
94543
Total Acres
3.7 linear mi
Parcel #
Various
State Highways
I-80, I-680, SR-12
Schools
Nelda Mundy, Solano Community College
Waterways
Suisun Creek, Green Valley Creek, and Dan Wilson Creek
Township
4N
Range
3W
Section
1

Notice of Determination

Approving Agency
Solano Transportation Authority
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print