UC Davis Unitrans Hutchison Bus Terminal
2 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2006102029
- Lead Agency
- University of California, Davis
- Document Title
- UC Davis Unitrans Hutchison Bus Terminal
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 2/5/2008
- Present Land Use
- Academic and Administrative
- Document Description
- UC Davis will construct a new bus terminal to serve up to 17 busses primarily for the Unitrans transit system. The project will include removal of an existing parking lot and removal of trees around the parking lot. Improvements for the project include installation of new landscaping, lighting, sidewalks, and bike racks to serve the new bus terminal. The project will take place in the Spring, Summer and Fall of 2008.
- Contact Information
-
Sid England
University of California, Davis
Lead/Public Agency
One Shields Avenue
Davis, CA 95616
Phone : (530) 752-2432
Location
- Cities
- Davis
- Counties
- Yolo
- Cross Streets
- Old Davis Road / I-80
- Zip
- 95616
- Total Acres
- 0.10
- State Highways
- SR-113, I-80
- Railways
- UPRR
- Airports
- University Airport
- Schools
- Davis Joint Unified
- Waterways
- Putah Creek
- Township
- 8N
- Range
- 2E
- Section
- 16
- Base
- MD
Notice of Determination
- Approving Agency
- University of California
- Approving Agency Role
- Lead Agency
- Approved On
- Final Environmental Document Available at
- 376 Mrak Hall, UC Davis, Davis, CA 95616
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- No
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- Yes
- (6) Findings were made pursuant to the provisions of CEQA
- Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.