City of Atwater Wastewater Treatment Plant Modification Project EIR

5 Documents in Project

Summary

SCH Number
2006101079
Lead Agency
City of Atwater
Document Title
City of Atwater Wastewater Treatment Plant Modification Project EIR
Document Type
NOD - Notice of Determination
Received
Posted
9/23/2008
Present Land Use
City GP: Manufacturing, Institutional, Zoning: Heavy Industrial (M-2) County GP: A-Agricultural, Zoning: A-1 - General Agricultural
Document Description
The project includes decommissioning and demolishing the existing 6-mgd wastewater treatment plant (WWTP) on Commerce Ave in the City of Atwater (City), except for the influent pump station; constructing a new 6-mgd WWTP on City-owned property along So. Bert Crane Road with upgrades to produce disinfected tertiary effluent; installing influent force mains to convey wastewater from the existing influent pump station to the new WWTP; and installing a new discharge.

Contact Information

Name
David Church
Agency Name
City of Atwater
Contact Types
Lead/Public Agency

Location

Cities
Atwater
Counties
Merced
Cross Streets
Commerce Avenue and North Applegate Road, Bert Crane Road south of SR 140
Zip
95301
Total Acres
~ 100
Parcel #
056-241-005, 007; 056-200-025, 026
State Highways
140
Railways
Southern Pacific
Schools
Ariel Dear Admy, Shaffer ES, Mitchell ES, Aileen Colburn ES, St.
Waterways
Atwater/Peck Drain, Bear Creek, Black Rascal Creek
Township
7S
Range
12E
Section
12, 35
Base
MDB&M
Other Information
Schools: Anthony School, Thomas Olaeta School, Bellevue ES, Elmer Wood ES, Fruitland Christian Preschool, Atwater HS.

Notice of Determination

Approving Agency
City of Atwater
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print