Millbrae WPCP Flow Equalization
4 Documents in Project
Summary
SCH Number
2006092018
Lead Agency
City of Millbrae
Document Title
Millbrae WPCP Flow Equalization
Document Type
NOD - Notice of Determination
Received
Posted
3/12/2008
Present Land Use
Industrial and Utility
Document Description
The Flow Equalization Project will install a new 1.21 million gallon flow equalization tank and associated pump stations, pipeline and other appurtenances at the City of Millbrae's Wastewater Pollution Control Plant. The project will also replace and or upgrade other on-site facilities and will construct a new 8,400 square foot Operations Center.
Contact Information
Name
Khee Lim
Agency Name
City of Millbrae
Contact Types
Lead/Public Agency
Phone
Location
Cities
Millbrae
Counties
San Mateo
Cross Streets
Millbrae Avenue / US 101
Zip
94030
Total Acres
4.5
Parcel #
024-371-0110
State Highways
US 101, 82
Railways
Caltrain, BART
Airports
San Francisco Intl Airport
Schools
Mills HS
Waterways
San Francisco Bay
Notice of Determination
Approving Agency
City of Millbrae
Approving Agency Role
Lead Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
No
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.