California Men's Colony Potable Water Distribution System Upgrade

4 Documents in Project

Summary

SCH Number
2006091075
Lead Agency
California Department of Corrections and Rehabilitation (CDCR)
Document Title
California Men's Colony Potable Water Distribution System Upgrade
Document Type
NOD - Notice of Determination
Received
Posted
4/4/2008
Present Land Use
The project is situated within the grounds of the California Men's Colony, the California National Guard's Camp San Luis Obispo, Cuesta College, and related public facilities. All improvements are within state or county-owned lands.
Document Description
CDFG is executing a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code to the project applicant, CA Dept. of General Services, represented by James Van Haun. The applicant proposes to install new water lines and upgrade existing ones to supply potable water to several State and County facilities. Project activities will include: installation of pipe bridge support structuers spanning Chorro Creek and below-grade/trench crossings of seasonal wetlands and/or minor tributaries, of Chorro Creek, replacement of, or improvement to, three existing crossings in Chorro Creek; and construction of, or improvement to, three pipeline sections adjacent to jurisdiction streams.

Contact Information

Name
Brian Erlandsen
Agency Name
California Dept. of Fish and Game
Contact Types
Lead/Public Agency

Location

Cities
San Luis Obispo
Counties
San Luis Obispo
Cross Streets
Highway 1 / Prison Entrance Road
Zip
93409
Total Acres
500
State Highways
1
Schools
Cuesta Community College
Waterways
Chorro Reservoir

Notice of Determination

Approving Agency
CDFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.

Download CSV New Search Print