San Diego Gas & Electric Company's Sunrise Powerlink Project
22 Documents in Project
Download CSV
New Search
Print
Summary
- SCH Number
- 2006091071
- Lead Agency
- Public Utilities Commission, California (California Public Utilities Commission)
- Document Title
- San Diego Gas & Electric Company's Sunrise Powerlink Project
- Document Type
- NOD - Notice of Determination
- Received
- Posted
- 11/29/2010
- Document Description
- DFG is intending to execute a Lake and Streambed Alteration Agreement pursuant to Section 1602 of the Fish and Game Code (SAA# 1600-2009-0365-R5) to the project applicant, San Diego Gas and Electric. The applicant proposes to alter various streams to construct a 500 kV transmission line from the Imperial Valley Substation to a new substation southeast of the town of Alpine, then continuing with a 230 kV transmission line with both overhead and underground components to the Sycamore Canyon Substation.
- Contact Information
-
Kelly Fisher
Department of Fish and Game
South Coast Region 4949 Viewridge Avenue
San Diego, CA 92123
Phone : (858) 467-4207
Location
- Cities
- El Centro San Diego
- Counties
- Imperial San Diego
- Cross Streets
- Numerous in Imperial and San Diego Counties
- State Highways
- S22, S2, SR78 and others
- Railways
- Numerous
- Airports
- Numerous
- Schools
- Numerous
- Waterways
- Numerous
- Other Location Info
- City/Nearest Community: Boulevard
Notice of Determination
- Approving Agency
- Department of Fish and Game
- Approving Agency Role
- Responsible Agency
- Approved On
- Final Environmental Document Available at
- California Public Utilities Commission 505 Van Ness Avenue San Francisco, CA 94102
Determinations
- (1) The project will have a significant impact on the environment
- No
- (2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
- Yes
- (2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
- No
- (2c) An other document type was prepared for this project pursuant to the provisions of CEQA
- No
- (3) Mitigated measures were made a condition of the approval of the project
- Yes
- (4) A mitigation reporting or monitoring plan was adopted for this project
- N/A
- (5) A Statement of Overriding Considerations was adopted for this project
- No
- (6) Findings were made pursuant to the provisions of CEQA
- No
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.