Sunrise Powerlink Project, San Diego Gas & Electric Company (CA Endangered Species Act Incidental Take Permit No. 2081-2010-022-05, Minor Amendment No. 1)

22 Documents in Project

Summary

SCH Number
2006091071
Lead Agency
California Public Utilities Commission (CPUC)
Document Title
Sunrise Powerlink Project, San Diego Gas & Electric Company (CA Endangered Species Act Incidental Take Permit No. 2081-2010-022-05, Minor Amendment No. 1)
Document Type
NOD - Notice of Determination
Received
Posted
8/29/2011
Document Description
Sunrise Powerlink is a new 500 kV and 230kV transmission line that SDG&E will build, operate, and maintain. Project construction began in the fall of 2010 and is expected to continue for ~30 months thereafter. Construction of the project includes 443 towers and poles, a new substation, permanent access roads, maintenance areas at structure sites, and permanent tower staging access areas for helicopters. DFG provides this notice following approval of minor amendment to the previously issued incidental take permit (IT) referenced above.

Contact Information

Name
Edward Pert
Agency Name
DFG
Contact Types
Lead/Public Agency

Location

Cities
El Centro, San Diego
Counties
Imperial, San Diego
Cross Streets
Numerous in Imperial and San Diego Counties
State Highways
S22, S2, SR78 and others
Railways
Numerous
Airports
Numerous
Schools
Numerous
Waterways
Numerous
Other Location Info
City/Nearest Community: Boulevard

Notice of Determination

Approving Agency
DFG
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above. You may also contact the OPR via email at state.clearinghouse@opr.ca.gov or via phone at (916) 445-0613.