San Diego Gas & Electric Company's Sunrise Powerlink Project
22 Documents in Project
Summary
SCH Number
2006091071
Lead Agency
California Public Utilities Commission
(CPUC)
Document Title
San Diego Gas & Electric Company's Sunrise Powerlink Project
Document Type
NOD - Notice of Determination
Received
Posted
1/11/2011
Document Description
The California Public Utilities Commission (CPUC) approved the Final Environmentally Superior Southern Route Alternative, which would include a 500 kilovolt (kV) transmission line from the Imperial Valley Substation to a new substation southeast of the town of Alpine, then continuing with a 230 kV transmission line with both overhead and underground components to the Sycamore Canyon Substation. Upgrades to the existing transmission system west of Sycamore Canyon Substation would also occur.
Contact Information
Name
Cliff Harvey
Agency Name
Division of Water Quality - 401 Certification and Wetlands Unit
Contact Types
Lead/Public Agency
Phone
Location
Cities
El Centro, San Diego
Counties
Imperial, San Diego
Cross Streets
Numerous in Imperial and San Diego Counties
State Highways
S22, S2, SR78 and others
Railways
Numerous
Airports
Numerous
Schools
Numerous
Waterways
Numerous
Other Location Info
City/Nearest Community: Boulevard
Notice of Determination
Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes
Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.