Tulare Beef Harvesting and Processing Plant

6 Documents in Project

Summary

SCH Number
2006081126
Lead Agency
City of Tulare
Document Title
Tulare Beef Harvesting and Processing Plant
Document Type
NOD - Notice of Determination
Received
Posted
9/19/2008
Present Land Use
Agricultural
Document Description
The project includes a 90-acre zoning change from Public Lands (PL) to Heavy Industrial (M-2), a General Plan Amendment changing the 90-acre's land use designation from Public to Heavy Industrial, issuance of a conditional use permit, approval of a parcel map separating the 90-acre section of land from 163-acre parcel and the 70-acre project site from the 20-acre residual parcel, and construction and operation of a beef harvesting and processing plant on the 70-acre site currently in agricultural production (cotton). The residual 20 acres of land to the east of the beef harvesting and processing site will be used for storm drainage purposes and will be zoned for future industrial development.

Contact Information

Name
Mark S. Kielty
Agency Name
City of Tulare
Contact Types
Lead/Public Agency

Location

Cities
Tulare
Counties
Tulare
Cross Streets
Paige Avenue and Enterprise Street
Zip
93274
Total Acres
90
Parcel #
174-040-001
State Highways
58
Waterways
TID Canals
Township
20S
Range
24E
Section
16
Base
MDB&M

Notice of Determination

Approving Agency
City of Tulare
Approving Agency Role
Lead Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
Yes
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
Yes
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
Yes
(6) Findings were made pursuant to the provisions of CEQA
Yes