Local Funding Mechanism for Comprehensive Flood Control Improvements for the Sacramento Area; Natomas Cross Canal South Levee Phase I Improvements

11 Documents in Project

Summary

SCH Number
2006072098
Lead Agency
Sacramento Area Flood Control Agency
Document Title
Local Funding Mechanism for Comprehensive Flood Control Improvements for the Sacramento Area; Natomas Cross Canal South Levee Phase I Improvements
Document Type
NOD - Notice of Determination
Received
Posted
4/25/2016
Present Land Use
Various, including flood control works, agriculture, and public right-of-way
Document Description
SAFCA proposes to update existing local funding mechanisms for implementing flood system improvements along the Sacramento and American Rivers, Natomas Basin, and the Sacramento Yolo Bypasses. The proposed project would update existing local funding mechanisms to support flood control improvements, some of which have been added or expanded to comply with Federal and State flood protection requirements established since the existing funding mechanisms were evaluated in a previous Program EIR, certified in 2007 (SCH2006072098).

Contact Information

Name
Tim Washburn
Agency Name
Sacramento Area Flood Control Agency
Contact Types
Lead/Public Agency

Location

Cities
Sacramento
Cross Streets
Various
State Highways
SR 99, 160, I-5, 80
Railways
Sierra Northern
Waterways
Sacramento&American Rivers & tribs, Yolo/Sac Bypasses Natomas Basin
Other Information
waterways: Natomas East Main Drainage Canal & tributaries

Notice of Determination

Approving Agency
DWR
Approving Agency Role
Responsible Agency

Determinations

(1) The project will have a significant impact on the environment
N/A
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
No
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
N/A
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA