Antioch Recycled Water Project

5 Documents in Project

Summary

SCH Number
2006072093
Lead Agency
Delta Diablo Sanitation District
Document Title
Antioch Recycled Water Project
Document Type
NOD - Notice of Determination
Received
Posted
2/13/2009
Document Description
The Delta Diablo Sanitation District Recycled Water facility proposes to expand its water reuse system. Under the Recycled Water Project, the District would extend the recycled water pipeline, using existing pipeline and constructing new pipeline, to establish recycled water service for use as landscape irrigation at the Lone Tree Golf Course, City parks and other green spaces along the alignment. The facilities include a total of 19,820 ft of underground pipeline, a pumping station and a below ground storage tank. The District has petitioned the State Water Resources Control Board for approval of a wastewater change petition for the Project. Pursuant to the petition, discharge into New York Slough will be reduced by 0.8 cubic ft per second.

Contact Information

Name
Meg Herston
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency

Location

Cities
Antioch
Counties
Contra Costa
Cross Streets
Vicinity of Pittsburg-Antioch Whighway, W. 10th Street, Lone Tree Way and Golf Course Road
Zip
Multiple
Parcel #
Multiple
State Highways
4
Railways
1
Schools
Several (Antioch USD)
Waterways
Contra Costa Canal, New York Slough (Delta)
Township
2N
Range
1E, 2E
Section
30, 31
Base
None

Notice of Determination

Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On

Determinations

(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
No
(6) Findings were made pursuant to the provisions of CEQA
Yes

Disclaimer: The document was originally posted before CEQAnet had the capability to host attachments for the public. To obtain the original attachments for this document, please contact the lead agency at the contact information listed above.

Download CSV New Search Print