Antioch Recycled Water Distribution System (Project); Water Recycling Grant No. 3231-030
5 Documents in Project
Summary
SCH Number
2006072093
Lead Agency
Delta Diablo Sanitation District
Document Title
Antioch Recycled Water Distribution System (Project); Water Recycling Grant No. 3231-030
Document Type
NOD - Notice of Determination
Received
Posted
11/13/2008
Document Description
The proposed project is a recycled water distribution system to expand recycled water service to the Lone Tree Golf Course and other City-owned parks within Antioch, CA. Project construction consists of (1) approx. 30,000 linear ft. of pipeline including 6,800 LF of 12 in. slip-lined pipeline utilizing an existing abandoned 18-in. pipeline, (2) a 1.1 million gal. underground storage tank located at the Lone Tree Golf Course, (3) a 180-horse power pump station to deliver recycled water from the tank to the golf course for irrigation and (4) a 162-hp vertical turbine pump at the District's Water Recycling Facility.
Contact Information
Name
Michelle Jone
Agency Name
State Water Resources Control Board
Contact Types
Lead/Public Agency
Phone
Location
Cities
Antioch
Counties
Contra Costa
Cross Streets
Vicinity of Pittsburg-Antioch Whighway, W. 10th Street, Lone Tree Way and Golf Course Road
Zip
Multiple
Parcel #
Multiple
State Highways
4
Railways
1
Schools
Several (Antioch USD)
Waterways
Contra Costa Canal, New York Slough (Delta)
Township
2N
Range
1E, 2E
Section
30, 31
Base
None
Notice of Determination
Approving Agency
State Water Resources Control Board
Approving Agency Role
Responsible Agency
Approved On
Determinations
(1) The project will have a significant impact on the environment
No
(2a) An Environmental Impact Report was prepared for this project pursuant to the provisions of CEQA
No
(2b) A Mitigated or a Negative Declaration was prepared for this project pursuant to the provisions of CEQA
Yes
(2c) An other document type was prepared for this project pursuant to the provisions of CEQA
No
(3) Mitigated measures were made a condition of the approval of the project
Yes
(4) A mitigation reporting or monitoring plan was adopted for this project
N/A
(5) A Statement of Overriding Considerations was adopted for this project
N/A
(6) Findings were made pursuant to the provisions of CEQA
Yes